Home

INSTALLATION MANUAL

image

Contents

1. ballasted 9 POST INSTALLATION TESTING WARNING Do not use air pressure to test tanks that contain flammable or combustible liquids or vapours The fuel air mixture may explode and cause death severe personal injury or property damage Tanks that will be ballasted with a flammable product should be air tested before ballasting SECOND INTERMEDIATE DEFLECTION MEASUREMENT After backfill is brought to the top of the tank make an intermediate measurement of vertical deflection according to the instructions in the Section 14 see Installation Checklist for deflection allowance TEST After the tank has been measured and vertical deflection is determined to be within the limits specified by Tank Solutions the tank must be tested to ensure that no damage occurred during installation Following the procedures in Section 2 soaping all exposed areas of the tank fittings and monitor the pressure for one hour Carefully relieve the pressure in the tank and remove the test assembly from the tank 8 WET HOLE INSTALLATION 10 BALLASTING CAUTION Never allow an empty tank to remain in a wet hole or a dry hole that may become wet unless anchoring and backfilling have been completed Failure to anchor and backfill may damage the tank or surrounding property Pump the water from the hole to maintain minimum water level Position anchors refer to Section 6 Add a minimum of 300mm of well placed backfill material to the hole and lev
2. 4 iI my r an ji S ES E ele ae m m mE 2x Width E FIGURE 6 1 TABLE 6 1 TANK DIA DEADMEN SLAB WIDTH M DIMENSIONS M W X D mm 150 x 150 300 x 300 450 x 300 Lay the deadmen in the excavation parallel to the tank and outside of the tank shadow see Figure 6 1 In multiple tank installations each tank will require two deadmen Revision A Page 5 of 14 The minimum spacing between tanks must be equal to twice the width of a single deadman One deadman may be used between two tanks if it is double in width Provide a separate anchor point for each hold down strap Deadmen are to be butted together where multiple sections are used Place A to A and AA to AA Marked on Deadmen ANCHOR SLAB An anchor slab is a reinforced concrete base The total length of the slab is 300mm greater than the overall length of the tank The minimum slab thickness is 200mm The width of the slab depends on the tank diameter Refer to Table 6 1 for specific dimensions Refer to Table 6 2 and Figure 6 2 for anchor point dimensions Provide a separate anchor point for each holddown strap When using a concrete base slab allow sufficient depth in the excavation for 300mm of bedding material below the tank TABLE 6 2 TANK DIA DIM A DIM B DIM F DIM E MIN MAX DIM GG D 1470 430 130 650 810 960 2850 2438 1143 838 381 1120 1370 4597 2
3. ANK FUEL CHEMICALS WATER Fibreglass Double Wall Tanks Liquid Filled Interstice INSTALLATION MANUAL Tank Solutions Pty Ltd ABN 59 142 807 949 513 Tomago Road TOMAGO NSW 2322 PO Box 102 RAYMOND TERRACE NSW 2324 Ph 61 2 4964 8270 e mail sales tanksolutions com au Tank Solutions Fibreglass Single amp Double Wall Tank Installation Manual Form F 938 Revision A Page 1 of 14 INTRODUCTION lt is important to follow the procedures and instructions in this manual in order to safely and properly install a Tank Solutions Underground Storage Tank Failure to follow these instructions will void the tank warranty and may cause tank failure serious personal injury or property damage The Tank Solutions warranty applies to a tank installed according to these instructions Since Tank Solutions does not control the parameters of any installation our sole responsibility in any installation is that presented in our warranty Use the Tank Installation Checklist accompanying this manual as the installation proceeds Retain a copy of the checklist along with any deviation authorisation letters certification etc in your files and return the original to Tank Solutions For Warranty to be effective the completed Installation Checklist must be returned to Tank Solutions within 30 days refer to Installation Checklist for more details Consult your Tank Solutions representative or distributor for a supply of additional check
4. Record the brine level on the Installation Checklist It is normal for the brine level to drop somewhat during transport however if no brine is visible in the monitor contact Tank Solutions WARNING Always secure the tank before moving or lifting it This is commonly done by connecting a crane to the lifting lugs Failure to do so could result in death or serious injury WARNING While moving or lifting the tank do not position any part of your body underneath the tank This could result in death or serious injury If damage is detected do not attempt repairs Contact the Production Manager at Tank Solutions on 02 4964 8270 After installation and before backfilling to grade testing must be repeated to verify that no damage has occurred during installation Remove all temporary service fitting plugs and the reservoir fitting plug Check the monitoring fluid level in the reservoir It should be about 1 full Visually check the interior of the tank for monitoring fluid There should not be any Replace the protective covers in the service fitting and the reservoir fitting 3 BACKFILL AND BEDDING Tank Solutions recommends tanks be installed using either pea gravel or crushed stone which meets the following specifications GENERAL The material is washed and free flowing and confirms to the specification of AS2758 and AS1141 No more than 5 by weight of the material may pass through a 2 36mm sieve Tank Solutions Fibre
5. 12 SUMPS BOTTOM FITTINGS If the tank has a sump or a bottom fitting take extra care that the tank does not rest on it prior to installation During installation provide a clear area in the bedding material so that the tank rests on the bedding and the sump or bottom fitting is clear After setting the tank fill and tamp the resulting void by hand before continuing the backfilling 13 BACKFILLING TO GRADE When the tank has been set tested and backfilled and all piping and venting has been completed the balance of the backfill material may be added When the tank has been backfilled to Sub Grade before concrete or asphalt take the final diameter reading Deflection reading B on the checklist The same material as specified in Section 3 must be used to completely fill excavation The backfill must be free of debris Any blocks or bricks used as support material during piping must be removed prior to completion of backfilling Safety measures such as placing barricades until installation is complete should be used around the excavation site Check and record the level of brine in the monitor fitting If the level has dropped significantly from the level recorded at the beginning of the installation process contact Tank Solutions immediately Be sure that the installation meets all of the requirements of minimum cover as specific in Section 4 Be sure that the checklist is properly completed 14 DEFLECTION MEASUREMEN
6. cured ensure that the manway fittings are sealed and proceed to fill containment sump Riser with water 2 Allow test to continue for one hour and observe joint for leaks Conclusion The riser is now ready for piping installation On completion of pipework and before back filling to grade repeat Testing 1 and 2 above The containment sump Riser should be water tight to eliminate ingress of ground water and the egress of any pipe leaks to the environment Note 1 In trafficable areas you MUST ensure that the foam quadrants are installed to prevent weight transfer to the riser tank 2 Install the driveway cover as per OEM instructions Tank Solutions Pty Ltd ABN 59 142 807 949 e sales tanksolutions com au w www tanksolutions com au New South Wales 513 Tomago Road Tomago NSW 2322 PO Box 623 Raymond Terrace NSW 2324 p 6124964 8270 f 61 2 4964 8522 Queensland Unit 3 40 Ingleston Road Wakerley Qld 4154 p 61733904800 f 61 7 3390 4667
7. of 150 m from the control panel Attached Manway Riser Probe if applicable and shown on the drawing The probe will be constructed of a material which is suitable for prolonged complete immersion in any of the fluids listed in U L Standard for Safety 1316 Table 14 1 all columns The probe will detect the presence of liquid in the riser when the liquid level has risen to a maximum of one inch above the bottom of the probe as located in its permanent mounting position The permanent mounting position is determined by the installer at the time of installation The probe will be capable of being mounted in the riser in a manner which allows adjustment of location The probe will be able to be mounted so that an increase in the liquid level does not interfere with the normal operation of the probe The probe mounting assembly supplied and installed by contractors will provide protection for the probe from the operational activities which may take place within the riser The probe will be capable of operating at a distance of 150 m from the control panel Operating Parameters Temperature Voltage 17 C to 65 6 C 110 or 220 VAC 50 60 Hz Performance The continuous hydrostatic monitoring system including the electronic amp the proves will be capable of detecting and alarming when the liquid level in the tank reservoir rises or drops 75mm to activate the sensing probe Materials The materials used in the monitoring system wi
8. or falls to predetermined alarm points The system will also include an electronic sensing probe to monitor the attached manway riser for the submersible pump if so specified Standards The double wall tank with a brine filled interstice will be listed by Underwriters Laboratories U L The electronic monitoring system used to monitor the liquid reservoir and the attached manway riser will also be listed by U L for intrinsic safety in a hazardous location Requirements for Liquid Filled Double Wall Tank The interstice of the double wall tank will be filled with a brine solution The tank will be delivered to the site with the brine solution in the interstice for all tanks up through 80 000 Litres Brine filling of interstice on 90 000 and 110 000 Litre tanks shall be done at job site by contractor The reservoir will be constructed of fibreglass and mounted directly to the top of the tank The reservoir will be fitted with one 100mm BSP fitting suitable for installation of the electronic reservoir probe The reservoir will have a capacity of 53 Litres for tank sizes 2 000 Litre through to 70 000 Litres and 151 Litres for tank sizes 80 000 through to 110 000 Litres Requirements for the Electronic Monitoring System The Controller The panel will receive the signal from the reservoir and or attached manway riser and provide for the following indications 1 System normal 2 System fault the fault indication must not be the same as
9. record the distance 5 Subtract the second distance from the first and record this value as reading B on the Installation Checklist CALCULATION AND COMPARISON oh Subtract reading B from reading A 2 Compare this value to the table of Maximum Allowable Deflections shown on the Installation Checklist 3 Vertical deflection in excess of these values indicates improper installation and voids the tank warranty 15 MONITORING SINGLEWALL TANKS Single wall tank installations may require release detection monitoring which can include inventory control automatic tank gauging vapour monitoring or ground water monitoring Check with state and local officials for requirements in your area DOUBLEWALL TANKS Tank Solutions double wall tank has an interstitial soace for the containment of leaked product from the primary tank The tank as supplied will have a minimum of one fitting that provides access into the space between the primary internal and secondary external tank shell walls If a double wall tank is sloped the monitor should be at the low end WITH A DRY INTERSTITIAL SPACE The monitoring system and method is the responsibility of the tank owner and or operator A safe electronic or mechanical system should be used to detect either incoming water or product The monitor system should detect leakage near the bottom of the tank Monitoring can be done through the access fitting provided IF the tan
10. top centre of tank Pull ends through anchor stirrups from inside to outside Lift ends to top of tank and secure NOTE When installing an FRP tank the straps are to be located on the rib in the guides supplied STEP 2 Locating the Binder WINDER SUPPORT METHOD Place the binder on the top centre line of the vessel Ensure that the strap is under the binder this helps to protect the vessel Pull the two loose ends of the strap over the binder so they are of equal length F 955 Rev B U x j U U 0 0 z 2 LL TA TAN FUEL CHEMICALS WATER STEP 3 Tensioning the Strap Using the Winding Mechanism STRAP RIGHT SIDE CLOCKWISE ie ae ROTATION WINDER STRAP POINT B METHOD Leave enough slack in the straps to achieve four 4 rotations of the winder approx 500mm Place both ends of the straps together through the slot in the winder shaft Wind the straps clockwise onto the shaft using a bar heavy screwdriver etc to achieve four 4 winds Use the tightening holes provided in the shaft Tension the strap to align holes in the winder and the base support while keeping tension on the strap insert bolt supplied and tighten nut Tank Solutions Pty Ltd ABN 59 142 807 949 e sales tanksolutions com au w www tanksolutions com au New South Wales 513 Tomago Road Tomago NSW 2322 PO Box 623 Raymond Terrace NSW 2324 p 61249648270 f 61 2 4964 8522 Queensland Un
11. 600 X Y Z 1 2 3 990 690 947 1862 2012 Position Strap Clip at Tank Top E nEri Typical Anchoring i yt guration a as o a F ma Ff H 2 i i L FIGURE 6 2 i i ME ES ES EET aE Mi E E a i IESE ll eea Fr a i pii Per eee kl zafo 2S ot ge ae Dg Pie See ee ae ad ea rA bis cea i iis mene e Ep i SSE HS Tank Solutions Fibreglass Single amp Double Wall Tank Installation Manual Form F 938 NOTE When fastening wire cable use a minimum of three clamps on each joint Use shackle type or chair type clamps as appropriate HOLDDOWN STRAPS Tank Solutions Hold Down Straps should be used when a tank is to be anchored The location of the straps are marked on the tank by the gt lt symbols An installation guide is provided as a separate booklet CAUTION Place the straps only in the locations designated by the arrow symbols gt lt A measurement must be taken of the tank diameter before the straps are tightened Measurement A on the Installation Checklist Refer to Section 14 for methodology To evenly distribute buoyancy loads tighten all hold down straps uniformly but cause no deflection of the tank An intermediate intermediate 1 measurement should be taken of the tank diameter after the straps have been tightened This should be compared with measurement A to ensure tank is inside the deflection
12. Inspection No evidence of damage found after setting in hole 13 Straps and tie downs positioned and secured according to installation instructions Backfill compacted Material has been tamped and or compacted to fill all voids around tank Tank properly ballasted during backfilling Tank s buried at proper depth to conform to appropriate conditions wet dry traffic or not POST INSTALLATION Verified By 17 Pressure Test Air soap test completed according to installation instructions Section 9 18 Internal Measurement The inside diameter of the tank has been measured and documented Dimension B Below Section 13 19 Brine Tanks A Check and record brine level in reservoir B Check for brine inside tank MEASUREMENT OF DEFLECTION All tanks must be measured to determine vertical deflection Follow deflection measurement instruction in the installation manual An initial deflection measurement is taken and recorded as a point of reference Subsequent measurements show tank deflection and can be compared to the table below Take each measurement from the same fitting using the same procedure Tank Maximum Nominal Inside Measurements Verified By Diameter Deflection Diameter mm I D before backfilling A mm mm DW I D after backfilling B 1470 1440 1440 DEFLECTIONS A B 3275 3150 3134 Measured at O End O Centre Mark Location of Note If Deflection is 75 of Maximum Deflection Readinas notify T
13. T Four deflection measurements should be taken 1 Initial measurement on placement of the tank in the hole measurement A on the Installation Checklist 2 An intermediate measurement when straps are tightened to ensure uniform tightening When backfill to top of tank is completed At Sub Grade before concrete or measurement B on the Installation Checklist PD asphalt topping DIPSTICK PREPARATION Revision A Page 8 of 14 Drive a small headed non sparking e g Brass nail halfway into a wooden dipstick 25mm up from its base FIRST DIAMETER READING PLACEMENT _ Place the dipstick into a socket fitting 2 Measure and record the distance from the tank bottom to the top of the fitting 3 Pull the dipstick up until the nail catches on the inside top of the tank 4 Measure the distance from the tank top inside to the top of the fitting Subtract 25mm from this measurement and record the distance 5 Subtract the second distance from the first and record this value as reading A on the Installation Checklist SUB GRADE DIAMETER READING 1 Place the dipstick into a socket fitting with a riser installed to sub grade 2 Measure and record the distance from the tank bottom to the top of the standpipe 3 Pull the dipstick up until the nail catches on the inside top of the tank 4 Measure the distance from the tank top inside to the top of the standpipe Subtract 25mm from this measurement and
14. a 13 2 mm sieve Crushed Stone Pea Gravel Aggregate Size Aggregate Size Steve Size Size Steve size j Aggregate Size _ Sieve Size 20mm 100 100 E 90t0100 100 90 to 100 100 i 13 2 mm 20 to 55 90to 100 40 to 70 85to 100 ee 9 5mm 0 to 15 40 to 70 sels 10t030 4 75 mm 0t05 0t015 a Pe as pe Ma Tank Solutions Pty Ltd ABN 59 142 807 949 e sales tanksolutions com au w www tanksolutions com au New South Wales 513 Tomago Road Tomago NSW 2322 PO Box 623 Raymond Terrace NSW 2324 p 61249648270 f 61 2 4964 8522 Queensland Unit 3 40 Ingleston Road Wakerly Qld 4154 p 6173390 4800 f 61 7 3390 4667 TAN FUEL K SOLUTIONS CHEMICALS WATER Double Wall Hydrostatic Monitoring Guide Specification For Hydrostatic Monitoring of FRP Underground Storage Tanks 1 0 2 0 3 0 4 0 4 1 4 2 General The tank manufacturer will supply a continuously monitored hydrostatic head pressure leak detection system The system will be designed by the manufacturer to detect a leak in either the primary tank or the secondary tank in either a wet or dry excavation The system will include a brine solution to prevent freezing delivered to the job site in the interstice of the double wall tank a reservoir mounted on top of the tank to provide a liquid medium for monitoring and an electronic monitoring system to sound an audible and visual alarm when the liquid level of the reservoir rises
15. allowance see Deflection Allowance table on Installation Checklist and Section 14 for methodology NOTE All exposed metal on the hold down straps turnbuckles and or threaded rod must be coated or galvanised to prevent corrosion 7 DRY HOLE INSTALLATION CAUTION Tank Solutions recommends that every site be thoroughly evaluated for the potential to trap water or otherwise subject the tank to a rise in the local water table Tank Solutions recommends that all tanks be anchored and ballasted in installations in which water could rise in the hole Failure to anchor and ballast the tank in a wet hole or one that can hold water may damage the tank or surrounding property Following installation of anchors prepare a smooth level bed 300mm thick to top of anchors of approved backfill material Place the tank or tanks onto the bed Do not set Tank Solutions tanks directly onto a concrete slab or on timbers cradles or directly onto the hole bottom Levelling As the tank is being placed set the tank pitch as shown on the site plans Tank Solutions does not require that a tank be pitched All pitch is determined by the tank owner s specification If a double wall tank is pitched the monitor should be at the low end Use the tops of the ribs to establish longitudinal level Establish lateral level by placing the level across the top of a fitting a manway or a collar When the tank is placed take the first internal diameter reading Deflecti
16. ank Solutions Technical Department g Tank Solutions Pty Ltd ABN 59 142 807 949 e sales tanksolutions com au w www tanksolutions com au New South Wales 513 Tomago Road Tomago NSW 2322 PO Box 623 Raymond Terrace NSW 2324 p 6124964 8270 f 61 2 4964 8522 Queensland Unit 3 40 Ingleston Road Wakerley Qld 4154 p 61733904800 f 61 73390 4667 TAN SOLUTIONS FUEL CHEMICALS WATER K FRP Riser Installation F936 REV A Page 1 of 2 Purpose Instructions for the on site installation for the FRP Riser to the underground tank 130 FOAM PACKING RISER 1200 Std FELO BONDED COLLAR MANWAY Items supplied with tank FRP Riser FRP Lid to suit 1 Above 4 x quadrants of foam Adhesive Kit ARN Method 1 Calculate height of riser to suit burial dimensions ensuring that all proposed pipe boot penetrations are clear of field joint Cut riser length T y T T k D 0 Q 2 IL Page 2 of 2 2 Position riser over FRP collar on the tank and tap gently into place ensuring a mechanical lock of the joint Ensure that the riser is level and that there is an equal spacing around the circumference of the internal joint 3 Seal the outside circumferential joint with duct tape to prevent loss of adhesive 4 Prepare the adhesive as per the package instructions and apply to the internal circumferential joint Allow curing time as per package instructions Testing 1 After joint has
17. blown about by the wind Uncontrolled movement of the tanks can cause death serious personal injury and property damage Before the tanks are unloaded or relocated on the job site e Be sure that all equipment used to lift the tanks is rated to handle the load e Prepare the unloading and or storage site by removing all rocks and debris e Arrange for sandbags or tyres to be used as chocks Use the lifting lug s when hoisting the tank Do not wrap chain or cable around the tank Tanks larger than 45 000Litres have multiple lifting lugs Use all of the lugs to move the tank See Fig 1 1 Use guy ropes to guide the tank when needed Do not move the tank by rolling FIGURE 1 1 Revision A Page 2 of 14 Whenever the tanks are stored at the site chock them in place to prevent rolling Tie them down if high winds are expected 2 PREINSTALLATION TEST 2 1 GENERAL Tank Solutions tanks are tested prior to shipment but the tank must be checked at the site prior to installation in order to verify the absence of shipping and handling damage Visually inspect the tank exterior and interior of the primary tank for damage and the presence of blue marker dye including external shell of the tank or on the tray of the vehicle Any damage should be documented and Tank Solutions contacted immediately If no damage is found complete the appropriate section on the Installation Checklist The Brine level should also be checked at this point
18. during the installation process the tank should be fully ballasted after the backfill is level with the top of the tank and after the post installation testing has been successfully completed Revision A Page 7 of 14 11 PIPING AND VENTING CAUTION All internal piping must be at least 100mm from the tank bottom Refer to Table 11 1 to determine the correct dimensions to size internal pumps and piping When the tank s interstitial space is filled with a liquid the space must be vented It is sufficient to drill a 4 diameter hole in the side or cap of the monitor system riser pipe When the groundwater level will be high enough to enter a drilled vent hole install a separate vent line from the riser pipe to above grade level When the interstitial space is dry it is not necessary to vent the space to atmosphere It is the installer s responsibility to select a thread sealant that is compatible with the product being stored Some sealants cannot be used with some products If necessary remove clean and re dope all plugs WARNING All underground tanks compartments shall be adequately vented to prevent the development of vacuum or pressure when filling or emptying the tank Failure to properly vent a tank or compartment could cause tank failure and result in death or serious injury WARNING Tank Solutions does not recommend pump or pressure filling of the tanks because an overfill or over pressurization could occur Over fi
19. el the bed to assure uniform bottom support for the tank Position the tank in the hole Partially ballast tank until it settles firmly on the prepared bed Ballast level in a tank must never exceed water level in hole during installation Use only enough ballast to sink the tank until backfill material is even with the top of the tank WARNING If product is used as ballast exercise special care in handling Safeguard against sparks fire or product spills Improper handling of product can cause a fire or explosion and death severe personal injury or property damage Tank Solutions Fibreglass Single amp Double Wall Tank Installation Manual Form F 938 WARNING If product is used as ballast exercise special care in handling Safeguard against sparks fire or product spills Improper handling of product can cause a fire or explosion and may result in death severe personal injury or property damage The tank may be ballasted after the backfill is even with the top of the tank and post installation testing has been successfully completed Only under wet hole conditions as described in Section 8 should ballast be added before the backfill is even with the top of the tank When filling the tank make sure the tank is properly vented The vent must be large enough to allow the displaced air to escape In general a tank is not adequately protected against floatation until the tank is fully backfilled and the top slab is in place Therefore
20. essive e Complete the air test outlined in Section 9 Post Installation Testing SUMMARY 1 Prepare the tank bed 2 Setand level the tanks 3 Measure the tank diameter 4 Install hold down hardware refer to Section 6 5 Conduct a visual inspection of the tank 6 Place and probe the first two lifts of backfill material 7 Add backfill to the top of the tank 8 Measure the tank diameter and complete the test After the air test and measurement of tank deflection are successfully completed it is recommended that the tank be ballasted until piping installation and final backfilling to grade is completed When filling the tank make sure that the tank is adequately vented The vent must be large enough to allow the displaced air to escape NOTE Do not ballast the tank until the backfill is even with the top of the tank WARNING If product is used as ballast exercise special care in handling Safeguard against sparks fire or product spills Improper handling of product can cause a fire or explosion and death severe personal injury or property damage After levelling tanks the anchoring procedures in Section 6 must be followed Backfill must be added evenly after anchoring and remaining dry hole backfilling procedures should be followed NOTE Cover depth must meet minimum depth specified in these installation instructions NOTE It is recommended that the tank be completel once backfill is even with the top of the tank
21. glass Single amp Double Wall Tank Installation Manual Form F 938 e EA D Pea Gravel PEA GRAVEL Mix of rounded particles sizes between 10mm and 20mm 14mm 10mm a amp AD i Crushed Stone CRUSHED STONE Mix of angular particles sizes between 10mm and 14mm lt is recommended that the supplier certify that the material conforms to AS2758 and any other applicable specifications For additional information refer to the Tank Solutions pamphlet Fibreglass Tank Backfill Guidelines NOTE If material which meets these specifications is not available contact the Tank Solutions Technical Service Department_for information on approved _ alternate materials and_ installation instructions Using other than approved bedding and backfill materials without Tank Solutions prior written approval will void the tank warranty and may result in tank failure 4 EXCAVATION PARAMETERS The installing contractor must take all precautions necessary to protect employees working in or near a tank excavation These precautions should include but are not limited to e Location and protection of any utility installations near the excavation before opening the excavation e Means of securing the walls of the excavation e Means of preventing exposure of employees to hazardous fumes from the excavation e Protection of employees from hazards associated with water accumulation in the excavation e Barricades etc to preven
22. incoming product The reservoir is designed to provide adequate capacity for normal thermal expansion and contraction STREET BOX CONCRETE PAD RISER PIPE SHORT DIP STICK RESERVIOR TAPE MEASURE OR DRY INTERSTITIAL SPACE AN ALTERNATIVE TO HYDROSTATIC MONITOR lf Tank Solutions tanks are purchased without the Hydrostatic Monitor the integrity of the primary and secondary tank walls may be physically monitored through a 100 mm fitting installed on each end of tanks 10 000 Litres capacity and above A single fitting is installed on 2 000 to 10 000 Litre capacity tanks By providing access to the tank bottom through the circumferential end ribs open to the interstitial soace a liquid sensor or a vacuum or air pressure monitoring system may be used LIQUID LEVEL Tank Solutions Pty Ltd ABN 59 142 807 949 e sales tanksolutions com au w www tanksolutions com au New South Wales 513 Tomago Road Tomago NSW 2322 PO Box 623 Raymond Terrace NSW 2324 p 6124964 8270 f 61 2 4964 8522 Queensland Unit 3 40 Ingleston Road Wakerly Qld 4154 p 61733904800 f 61 7 3390 4667 A Out of Hole Tie TANK Down system FUEL CHEMICALS WATER Installation Instructions STEP 1 Locating the Strap CENTRE OF STRAP STRAP END STRAP END ANCHOR ANCHOR STIRRUP STIRRUP CJ DEADMAN ANCHOR DEADMAN ANCHOR METHOD Find the centre of the length of strap provided e Place the centre of strap on
23. ion that identifies the size or gradation of the material If a specification for the material is not available an independent testing laboratory can provide a sieve analysis on a sample of the backfill material The sieve analysis or material specification can then be compared against size requirements for the crushed stone or pea gravel WARNING An important characteristic of good backfill material is hardness or stability when exposed to water or loads Most materials have no problem meeting the hardness requirement Materials like soft limestone sandstone or shale should not be used as backfill because they break down over time If in doubt about backfill contact Tank Solutions Pty Ltd F 907 RevB i a m U i L 0 ii y 2 L single Wall AN IK amp Double Wall FUEL CHEMICALS WATER STANDARD SIZES OF COARSE AGGREGATE THAT MEET CRUSHED STONE OR PEA GRAVEL SPECIFICATIONS The first column of each table identifies the standard sieve sizes that are used to grade aggregate material The remaining two columns have a standard aggregate size range For each aggregate size the amount of material finer than each laboratory sieve Square openings is given as percentage of the total weight of the sample These percentages give an indication of the particle size distribution within the given aggregate size For example 20 mm pea gravel aggregate size 20 to 55 of the sample measured by weight should pass through
24. it 3 40 Ingleston Road Wakerly Qld 4154 p 6173390 4800 f 61 7 3390 4667 F 927 RevA TAN Double Wall BSSLuTions M Wet Interstice Installation Checklist INSTALLATION SUPPLEMENT TANK HANDLING DATA Single Wall Actual Double Wall Nominal Nominal Actual Single Wall Double Wall Length _ Capacity Capacity Shipping Capacity Shipping na Litres Litres Weight Kg Litres Weight Kg 1470 2 000 2 500 150 2 400 300 1 700 1470 5 000 5 300 300 5 100 500 3 300 2600 50 000 50 600 2 600 49 800 3 900 10 945 2600 55 000 56 800 2 900 56 000 4 300 12 200 2600 60 000 60 900 3 100 60 000 4 600 13 070 3275 70 000 69 900 2 200 69 400 4 200 9 994 3275 80 000 79 800 2 600 79 200 4 700 11 254 3275 90 000 91 600 2 900 89 000 5 100 12 514 3275 100 000 102 000 3 100 102 000 5 600 14 194 3275 110 000 111 200 3 300 108 600 6 700 15 034 INSTALLATION CHECKLIST Double Wall Underground Fibreglass Storage Tank s The installing contractor must read the installation manual and complete and return this checklist within 30 days after the date of installation to validate the Tank Solutions warranty The tank owner must retain a copy of this checklist and a copy of all deviation authorisations to substantiate any warranty claim U x C 0 Le U U k Date of Installation Tank size and capacity Tank Type Please Circle SW DW SC DC TC Tank Number Site Owner Site Address ee Street City State Postcode Installing Co
25. k is sloped during installation the lowest elevation must be the monitoring end Tank Solutions Fibreglass Single amp Double Wall Tank Installation Manual Form F 938 HYDROSTATIC MONITORING SYSTEM In a liquid filled monitoring system the interstitial space is filled with liquid at the point of manufacture except 95000 and larger litre tanks The system provides continuous leak protection and it enables the owner to conduct a tank tightness test It also provides the ability to use an electronic monitoring system 16 ADDING TANKS AT EXISTING LOCATIONS Additional Tank Solutions tanks can be installed at existing locations if proper foundation support exists The method of installation is the responsibility of the owner It is required however that one of the following methods be used The preferred method is to install a new tank in a separate hole at least 1 Metre from the original hole Caution must be exercised in keeping unusual surface loads off existing tanks The natural barrier of undisturbed soil between tanks must be maintained ai oa Limi Sh ear Sen T alla EN memi a E i E ian SS see a SL Hy H WS ee ail cP ill f SUHTES Sie ES If this method is not practical additional tanks may be buried in the same installation hole After emptying existing tanks to less than one quarter capacity remove the surface pad Enlarge the excavation f
26. list forms Comply with all applicable regulations and standards such as e national state and local construction environmental codes e industry standard practices eg PEI RP100 API RP1615 amp EPA CP 4 AS1692 AS1940 health safety and For additional information contact your state and local government authorities including health fire or building departments and environmental agencies All work must be performed according to standard industry practices and OH amp S regulations A Tank Solutions requirement will never take precedence over a requirement imposed by any federal state or local code or regulation In all cases any such requirement takes precedence over any provision of the Tank Solutions manual Tank Solutions must authorise any variation to or deviation from these instructions This authorisation must be made in writing prior to tank installation DEFINITIONS Throughout this text these definitions will apply e Socket fitting a fitting either on a manway or on the tank shell which opens into the primary containment vessel where the tank s contents are normally stored Monitor fitting a fitting located on the tank shell which opens into the secondary containment vessel which is the normal monitoring location on the tank For additional terminology see Figure 0 1 UFTAG LLG MANWAY WITH FITTINGS FIGURE 0 1 Tank Solutions Fibreglass Single amp Double Wall Tank Installation Ma
27. ll be corrosion resistant to the liquid used to fill the interstice The liquid used to fill the interstice will not be corrosive to the materials of construction of the fibreglass tank Installation The monitoring system will be installed in accordance with the manufacturer s installation instructions and all applicable federal state and local laws and regulations F U x 0 Le U U k i SOLUTIONS FUEL CHEMICALS WATER Fibreglass Tanks Double Wall WET INTERSTITIAL SPACE MANUALLY CHECKING TANK INTEGRITY WITH A HYDROSTATIC RESERVOIR During piping a 100 mm PVC riser pipe with 5mm vent hole is fastened to the fitting atop the reservoir This will be cut to a level below a street box and secured with a threaded cap The reservoir liquid level and the tank s integrity can then be visually checked with a dipstick A liquid level of 150 mm from the tank top should be maintained In the unlikely event of a tank leak the liquid will drain from the reservoir If the leak is in the interior wall the monitoring fluid will drain into the primary tank and can be detected with a water finding paste at the tank s bottom Should a leak occur in the outer wall the monitoring fluid will also drain from the reservoir and interstice into the gravel environment No water will be detected in the primary tank The liquid level in the reservoir will fluctuate with the temperature differential of
28. lling the tank while under pressure could cause tank failure even if the tank vent is unrestricted Tank failure could result in death or serious injury WARNING If owner operator allows pump or pressure filling of the tank owner operator must ensure that the tank is not equipped with overfill protection such as an automatic shut off device or ball float valve Owner operator must notify whoever will fill the tank that automatic shut off equipment is required on the delivery truck to prevent an overfill and that over filing the tank while under pressure could cause tank failure even if the tank vent is unrestricted Failure to follow these instructions each time the tank is filled could cause an overfill over pressurization or tank failure and could result in death or serious injury TABLE 11 1 INTERIOR DIMENSIONS mm Tank Solutions Fibreglass Single amp Double Wall Tank Installation Manual Form F 938 3 3 3196 3323 3150 3189 3316 3134 NOTE All piping must conform to all applicable codes and standards See INTRODUCTION WARNING When pressure testing the piping the tank must be isolated from the piping systems The test pressures for piping may cause the tank to explode and cause death severe personal injury or property damage CAUTION When extending monitoring or vapour recovery piping to the surface be sure that the at grade fittings are different from any fittings and will not accept standard fill hoses
29. n ultimate bearing capacity of less than 168 kpa m or where soil will not maintain a vertical wall the excavation must allow a minimum space equal to 2 the diameter of the tank between the side and endcap of the tank and the excavation wall The spacing between adjacent tanks 450mm remains the same FILTER FABRIC The tank owner or his technical representative is responsible for determining whether filter fabric or an alternate filtering technique is appropriate for a specific installation Filter fabric allows the passage of water but prevents the migration and mixing of native soil and backfill material It preserves the integrity of the backfill envelope which supports the tank Polyethylene film is not considered an effective material to prevent migration of pea gravel and native soil it may tear or degrade while in service Tank Solutions recommends that filter fabric be used when the tank may be installed in e Areas with frequently changing ground water conditions or areas subject to tidal fluctuations e Unstable soils such as bog swamp landfill or mud e Wet conditions with silty soil For further information concerning fabric specifications and installation procedures consult the filter fabric supplier s installation guides or instructions To install filter fabric typically filter fabric manufacturers recommend that the installer line the excavation sides and bottom with the fabric Overlap adjoining panels by at lea
30. ntractor Contractor Address Street City State Postcode Supervisor On Site Fibreglass Tanks F 927 Rev A T AN Double Wall SOLUTIONS BSSLuTions M Wet Interstice PRE INSTALLATION Verified By 1 Visual Inspection No evidence of damage holes cracks gouges in tank document any damage found 2 Brine Tanks A Check and record brine level in reservoir B Check for brine inside tank 3 Backfill material indicate which type A Crushed stone or pea gravel as specified by FTS B Other describe requires specific approval by FTS 4 Excavation Hole dimensions are correct as per installation instructions for appropriate conditions 5 Internal Measurement The inside diameter of the tank has been measured and documented Dimension A Below 6 Filter Fabric Utilised Indicate one A Yes B No 7 Hole Condition Indicate one A Dry hole Water not anticipated to reach tank Area not subject to flooding B Wet hole Excavation may trap water Area subject to flooding 8 Traffic Loads Indicate one A Traffic loads anticipated B No traffic loads 9 Anchoring Performed in accordance with installation instructions A Concrete Anchors B Full slab DURING INSTALLATION Verified By 10 Backfill material bed is level and is a minimum of 300mm deep over native soil or slab before setting tank Tank spacing Tanks are spaced correctly from each other and excavation walls according to instructions Visual
31. nual Form F 938 If you have any questions or encounter any situations not covered in these installation instructions contact the Tank Solutions Technical Service Department on 02 4964 8270 SAFETY Before beginning the tank installation read through the entire installation manual It is the installers responsibility to comply with all safety precautions codes and regulations No instructions or procedures presented in this manual should be interpreted as to put as risk any person s health or safety or to harm any property or the environment Keep the Installation Manual available at the installation to refer back to safety procedures as needed The following definitions will serve as a guide when reading the Installation Manual WARNING indicates hazards which if not avoided could cause death serious personal injury or significant property damage CAUTION indicates hazards which if not avoided may cause personal injury or property damage 1 PREPARATION FOR INSTALLATION WARNING Working in excavations is dangerous and is regulated by safety codes Careless activity or operation of equipment can cause death or serious personal injury Although the corrosion resistant Tank Solutions tanks are rugged care must be taken that they are not dropped or damaged during delivery unloading and handling on the job site WARNING The tanks are heavy and have a large surface area The tanks will roll on sloped surfaces and can be
32. on reading A on the checklist See Section 14 for instructions on taking deflection readings Before backfilling do a visual inspection on the tank if no damage is found note this on the Installation Checklist and continue to follow these instructions If damage is found contact Tank Solutions BACKFILLING Use only approved backfill material See Section 3 approved material with sand or native soil as backfill material All excavated native soil must be replaced with approved material Place one 300mm lift of material evenly around the tank From the hole side or the top of an adjacent tank work the material by hand completely beneath the tank body and domes to provide full support Use a probe long enough to reach beneath the tank and push the backfill in place Repeat this setup with a second 300mm lift After the second lift of material has been placed and probed the backfill can be brought to the top of the tank without further hand work Do not mix Do not use native soil Revision A Page 6 of 14 CAUTION Do not strike the tank with the tamping bar tank may be damage and require repair The When the tank is backfilled to the tank top e Take a second intermediate diameter reading as an in process check compare to the original measurement A to ensure the tank does not lie outside the maximum deflection range outlined on the Installation Checklist DO NOT proceed to grade if the deflection is exc
33. or the new tank leaving as much backfill as possible around existing tanks It may be necessary to install shoring to make sure that existing tanks do not move and that sufficient backfill remains The new tanks must be installed by following the procedures in this guide Remember to leave minimum of 450mm between tanks The backfill material must be the same as that specified in Section 3 Revision A Page 9 of 14 single Wall TANK amp Double Wall FUEL CHEMICALS WATER Backfill Guidelines BACKFILL MATERIAL CRUSHED STONE OR PEA GRAVEL The backfill material surrounding a Fibreglass tank is a critical part of the installation This data sheet provides guidelines for choosing the best material when installing Fibreglass tanks Tank Solutions Pty Ltd recommends that either crushed stone or pea gravel is used as a backfill material 1 CRUSHED STONE should be washed and free flowing Angular particle size should be between 10 mm and 14 mm 2 PEA GRAVEL rounded particles river gravel deposits must have a nominal diameter of 10 mm and a maximum diameter of 20 mm Australian Standards AS2758 1 AS1141 11 AS1141 12 AS1141 24 and AS1141 34 have been used to specify the aggregate required for backfill The standard sizes of coarse aggregate that meet Tank Solutions crushed stone or pea gravel specifications are given in the table on the back page of this data sheet Suppliers should be able to provide a specificat
34. rom the slab to the tank There must be a minimum 150mm space between the bottom of the slab and the top of the riser 5 TANK SPACING NOTE These are minimum spacings and must be increased as needed to accommodate deadmen or anchor slabs Refer to Section 6 on tank anchoring Always allow sufficient clearance to allow the deadmen to be set outside of the tank shadow The relevant Australian Standard AS1940 specifies the minimum tank separation distances Te e by Te SS SST SS an Tanks not subjected to traffic loads must have a minimum cover depth of 600mm of backfill or 300mm backfill plus 100mm of reinforced concrete or 150mm of asphalt STABLE SOIL CONDITIONS We Where shoring is not required to maintain a vertical wall from top to erie bottom of the excavation the minimum spacing between the sidewall or endcap of the tank and side of excavation must be DRY x CONDITIONS EM 450mm If more than one tank is to be installed in the same hole ap eres il il there must be at least 450mm between the tanks eo EE Tank Solutions Fibreglass Single amp Double Wall Tank Installation Manual Form F 938 Revision A Page 4 of 14 T m I MES M 1 2 TANK DIA 172 TANK DIA ee a ee ene ME AAAA MESIE Eg UNSTABLE SOIL CONDITIONS If the soil has less than 36 kpa m cohesion as calculated from an unconfined compression test or soils having a
35. st twelve inches Place backfill material on the panels around the edge of the hole to anchor them in place In wet hole conditions use backfill material to sink and hold the fabric in place on the bottom of the hole 6 ANCHORING TANK HOLD DOWN STRAPS CAUTION Tank Solutions recommends that every site be thoroughly evaluated for the potential to trap water or otherwise subject the tank to a rise in the local water table Tank Solutions recommends that all tanks be anchored in installations in which water may enter the hole Failure to anchor may damage the tank or surrounding property Tank Solutions Fibreglass Single amp Double Wall Tank Installation Manual Form F 938 WARNING Only use the anchor points when lifting and positioning the deadmen A spreader bar may be required to lift longer sections of deadmen Use guy ropes to guide the deadmen when lifting Failure to do so could result in death or serious injury DEADMAN ANCHOR A deadmen is a reinforced concrete beam with a total length 300mm greater than the overall length of the tank A deadmen may be fabricated in multiple sections as long as the total length is not decreased and each section contains at least two anchor points The width and thickness depend on the tank diameter Table 6 1 for specific dimensions Refer to l ai os m r Lil nter ail Him IE e i pe
36. t unauthorised vehicle or pedestrian traffic e Inspection of the excavation and surrounding area at least daily Revision A Page 3 of 14 The minimum depth of the excavation is normally determined by the Tanks in high water areas not subjected to traffic loads must have a presence or absence of groundwater and the presence or absence minimum of 1 Metre of backfill covering and must be anchored of traffic at the site These dimensions are critical to the successful installation of a tank Tanks subjected to traffic loads must have a cover depth of at least 450mm of backfill plus 230mm of asphalt An acceptable alternative is a minimum of 450mm of backfill plus 150mm of reinforced concrete Ele DRY Bis bs i WARNING In a non traffic installation ensure that the areas er STS above the tanks will never be subject to traffic load which could cause tank damage and result in death or serious injury S SMES SE ISIE g i eee UL ea TT es m ME ql w a SETS NOTE These depths of cover are MINIMUMS in all cases NOTE Asphalt and concrete pads must extend a minimum of 300mm beyond tank in all directions Tanks subjected to traffic loads and high water must have a minimum of 760mm of backfill and either 230mm of asphalt or NOTE Maximum burial depth is 2 1m of cover over top of tank 150mm of reinforced concrete and must be anchored NOTE Manway riser if present must not transmit load f
37. the alarm indication 3 System leak alarm Also a system test switch indicating the system is functional will be provided All alarms will be both audible and visible Unit will be able to be reset The control panel will provide an indication of which tank is in the alarm condition if more than one tank is being monitored The system will provide intrinsic safety at the probe locations Reservoir Probe The probe will be constructed of a material which is suitable for prolonged complete immersion in the monitoring liquid 4 3 4 4 5 0 6 0 7 0 The monitoring liquid may be Salt Brine up to 30 CaCl in water The probe will detect and report a change in liquid level either above high alarm point or below low alarm point the neutral level established during the initial filling and subsequent maintenance of the system The probe will not operate by inducing an electrical current into the liquid medium which is being monitored The sensing range represents a build in allowance for pressure and thermal variation Until the liquid level exceeds the allowable variation the probe will not send a signal to the monitor unit The probe will be capable of being mounted in the reservoir in a manner which allows adjustment of location The probe must be able to be mounted so that normal fluctuations of the liquid level do not interfere with the normal operation of the probe The probe will be capable of operating at a distance

Download Pdf Manuals

image

Related Search

Related Contents

Expandable Ethernet IO controller  Bedienungsanleitung - CS  OPC-F1-ETH user`s manual V1.100 - Fuji Electric Corp. of America  Elite Servozoom 250 mode d`emploi  Samsung Galaxy Note (8.0, 4G) manual de utilizador  g-2 医療機器又は体外診断薬 は以下に示すりスクが調的 かつ適切に  User`s Manual - Ness Corporation  IH 025 VOLCANO  OC Pro Complete Help Guide - English  104-461A - Animas Canada  

Copyright © All rights reserved.
Failed to retrieve file